GREENERGY POWER (I) PVT Ltd
Submitted to: Prof. D. Shreenivasachary
Submitted by: Nikhlesh Jindal-10BSPHH010968 Ankit Grover-10BSPHH010099 Anuj Grover-10BSPHH010134 Nitika Thakur-10BSPHH010491 Nabarun Saha-10BSPHH010428
INDEX EXECUTIVE SUMMARY……………..……………………………………………………………………2 PROJECT AT A GLANCE……………………………………………………………………………….…3 SECTION – 1 INTRODUCTION TO THE PROJECT………………………….…………………………………………6 SECTION - 2 PROJECT DESCRIPTION………………………………………………………………...……………….10
SECTION - 3 DEMAND ANALYSIS AND JUSTIFICATION OF THE PROJECT…………………..………………12
SECTION - 4 TECHNICAL FEATURE & EQUIPMENTS OF THE PLANT…………………………………………15
SECTION-5 POWER PLANT CONFIGURATION AND SPECIFICATIONS OF MAIN PLANT EQUIPMENT……………………………………………………………………………………………...…17
SECTION - 6 OPERATION AND MAINTENANCE……………………………………………………………………..31
SECTION - 7 SWOT ANALYSIS…………………………………………………………………………………………..37
SECTION - 8 PLANT LAYOUT & PROJECT IMPLEMENTATION……………………………………...………….40 SECTION – 9 ESTIMATED PROJECT COST……………………………………………………………………………42 SECTION – 10 ESTIMATED POWER GENERATION COST…………………………………………………………...44
1|Page
(A)
EXECUTIVE SUMMARY The Electricity Act, 2003, paves way for an innovative approach to solve our country’s power problems. It has paved the way for a competitive environment; open access to existing transmission and distribution network to transmit electricity across regions; de-licensing of generation, captive power and dedicative transmission lines; licensing of distribution and supply companies and the restructuring of State Electricity Boards
The Ministry of Power have a mandate to promote cogeneration and renewable sources for Power generation under Nodal agencies and hence it will play a major role in mainstreaming renewable energy sector.
The advantage or renewable
resources includes their capacity to produce energy without producing carbonbased warming and polluting agents into the atmosphere. The financial cost of its applications is not always cheap but if the environmental costs of using fossil are accounted for, renewable energy wins hands-down. There are also indirect savings on health and its costs as there are no harmful emissions.
In the above backdrop, Sahil Energy Pvt. Ltd., has decided to set up a 5MW Solar Power Plant. This Detailed Project Report (DPR) brings out all technical details and overall costs justifying the selection of the project. The total power generation is envisaged to be 5MW from Solar Photovoltaic Cell. It is a very important document that is required for Environmental Impact Assessment (EIA) studies, fixation of tariff, finalizing Power Purchase Agreement (PPA) and also for submission to Financial Institutions for obtaining project funding. The total project cost is expected to be Rs85 Crores and the average cost of generation is expected to be Rs.12.86 /kWh.
2|Page
(B)
PROJECT AT A GLANCE
1.0
GENERAL
1.1
The Project
5MW Solar PV Grid Connected Power Project
1.2
Owner
SAHIL ENERGY
1.3
Location of Plant
ANANTAPUR DIST.
1.4
Location
Kadiri
1.5
Distance from District Headquarter
1.6
Access by Road
Chennai Mumbai National highway
1.7
Access by Rail
Kadiri Railway station
1.8
Access by Air
Satya Sai Airport Anantpura
1.9
Telecommunications
Telecommunication facility available
1.10
Land
It is proposed to install 5MW on the land, admeasuring about ………… Acre, which is already demarcated
1.11
Land Characteristics
Barren Land Non Agricultural Land
1.12
The Geographical location of the project site
13'-40' and 15'-15' Northern Latitude and 76'-50' and 78'-30' Eastern Longitude
1.13
Irradiation details considered
Kadiri, Anantpur(Dist.)
1.14
Type of Module Mounting Structure
Fixed Structures, Earth Mounted
1.15
Type of PV Modules Considered for Crystalline the offer
1.16
Proposed Capacity
5 MWp
1.17
Capacity of each PV Module
200 Wp
1.18
Invertors Capacity
100 KVA x 50 Nos.
1.19
Projected Energy Production per year
8.3 MU(Assured)
3|Page
1.20
Total Project Cost
4|Page
Rs 80. CR
SECTION - 1 INTRODUCTION TO THE PROJECT
5|Page
INTRODUCTION World Economic growth is driven by energy, whether in the form of finite resources such as coal, oil and gas or in renewable forms such as hydroelectric, wind, solar and biomass or its converted form.
This energy generation and consumption
strengthens the nation’s industries, vehicles, homes and offices.
It also has
significant impact on the quality of the country’s air, water, land and forest resources. For future growth to be both rapid and sustainable, it needs to be as resource efficient and environmentally benign as possible. GENERATION OF ELECTRICITY & IMPORTANCE OF RENEWABLE ENERGY The growth in installed power generating capacity has not kept pace with the projected demand. To solve this problem, it is necessary to set up more power plants and most of these power plants will be either fossil fuel based or hydro electric units. However, the conventional power stations cause enormous damage to be environment due to pollution and other side effects. Renewable energy sources energy source are wonderful options because they are limitless. These will not be exhausted though fossil fuel will be gradually exhausted in course of time. Also another great benefit from using renewable energy is that most of these sources do not pollute the environment; the way burning of fossil fuels dose. SOURCE OF GREENHOUSE GAS The greenhouse gas emissions (GHG) come primarily from the combustion of fossil fuels in energy use. Energy use is largely driven by economic growth with shortterm fluctuations in its growth rate created by weather patterns affecting heating and cooling needs, as well as changes in the fuel used in electricity generation. The burning of fossil fuels produces around 21.3 billion tones of Carbon Dioxide per year, but it is estimated that natural processes can only absorb about half of that amount, so there is a net increase of 10.65 billion tones of atmospheric carbon dioxide per year. Carbon dioxide is one of the GHG that enhances radioactive forcing and contributes to global warming, causing the average surface temperature of the earth to rise. Environment scientists predict that this will cause major adverse effects, including reduced biodiversity.
6|Page
The electricity sector is unique among industrial sectors in its very large contribution to emissions associated with nearly all air issues. Electricity generation produces a large share of nitrogen oxides and sulphur dioxide emissions, which contribute to smog and acid rain and the formation of fine particulate matter in addition to carbon dioxide. In addition, this sector has significant impacts on water and habitat and species. In particular, hydro dams and transmission lines have significant effects on water and biodiversity WORLD ENERGY SCENARIO It was estimated that in 2005, 86% of primary energy production in the world came from burning fossil fuels, with the remaining non-fossil sources being hydroelectric 6.3%, nuclear 6.0%, and renewable energy sources, i.e. geothermal, solar, wind, biomass and wastes contributed only 0.9%. BACKGROUND OF THE PROJECT Large multi-megawatt PV plants, approximately to 50 MW, are now in operation in the world. Solar Photovoltaic (PV) is known to be an important energy source for developing countries like India. Its importance is now being reaffirmed even by developed countries in view of its renewable and environment friendly character.
In our
country also, optimum utilization of solar energy could not only lead to savings in conventional energy but also result in many indirect benefits. In India 2MW solar PV now are commercially operated by independent power producer. But till now solar technology is expensive compared to other technology and significant financial assistance from government is needed to the developers and operators of new plants. In view of this, the Ministry of New & Renewable Energy Sources has been promoting electricity generation from Solar PV in Mega-Watt level. These projects are covered under the Grid Interactive Solar PV Power Generation Projects of Ministry of New & Renewable Energy Sources, Govt. of India. The Ministry initiated the programme to establish as a viable and environment friendly electricity generation option.
7|Page
BARRIERS IN DEVELOPMENT OF THE PROJECT
The project has been identified with some barriers as mentioned below: (a)
Higher capital cost – The initial capital investment of the project is so high compared to other conventional power Project, so per MW cost is high.
(b)
Low Capacity Utilization factor – the total unit generation is low compared to other electricity generation system, because maximum of 6 hours in a day plant gets the solar light and generates the power.
The project being first of its kind in the state, thee could be more risks and barriers which might surface as the project progresses and it is difficult to enumerate all at this stage. BENEFITS OF GRID CONNECTED SOLAR PV POWER PLANT (a)
Power from the sun is clean, silent, limitless and free
(b)
Photovoltaic process releases no CO2, SO2 or NO2 gases which are normally associated with burning finite fossil fuel reserves and don’t contribute to global warming.
(c)
Photovoltaics are now a proven technology which is inherently safe as opposed to other fossil fuel based electricity generating technologies.
(d)
No fuel is required for generation, so fuel cost of power generation is zero.
(e)
Solar power shall augment the needs of peak power needs
(f)
Increase the grid reliability i.e., voltage and frequency
(g)
Solar Powered Grid Connect Plants can act as tail end energizers, which in turn reduces the transmission and distribution losses.
(h)
Provides a potential revenue source in a diverse energy portfolio
(i)
Assists in meeting renewable portfolio standards goals
(j)
Generation of electricity from Solar PV is totally free of Green House Gas emission.
8|Page
SECTION - 2 PROJECT DESCRIPTION
9|Page
INTRODUCTION The proposed 5MWp solar power plant project will generate electricity from non-conventional sources. The project will use “polycrystalline” technology for the first time in the state for producing power by solar energy.
This
project envisages generation of safe, reliable electricity in an environmentally friendly way. BRIEF DETAILS OF PROJECT AREA Kadiri
is a taluka under Anantpura District situate in
Proposed Solar Power Plant is situated in Kadari
Land area of power plant
10 | P a g e
:
20Acres
Andhrapradesh
SECTION - 3 DEMAND ANALYSIS AND JUSTIFICATION OF THE PROJECT
11 | P a g e
INTRODUCTION It is well know fact that electricity is the most essential input for growth and development of any state. Andhra pradesh is planning to go rapidly in both the industrial and agricultural sectors and consequently the demand for power is on the rise. However, despite Andhrapradesh possessing immense potential of power ranging from Coal to natural gas not taken place on a scale commensurate with the possibilities. As a result there exists a big gap between conventional and Nonconventional power generation for power in the State. SOLAR POWER POTENTIAL IN INDIA India is endowed with rich solar energy resource. The average intensity of solar radiation received in India is 200 MW/km square (megawatt per kilometer square), but the amount of solar energy produced in India is merely 0.5% compared to other energy resources till date India just have 2.12 megawatts of grid-connect solar generation capacity. As part of the National Solar Mission, the ministry aims to booster the annual photovoltaic production to at least 1,000 megawatts a year by 2017. With an installed capacity of 123 GW, the country currently faces energy shortage of 8 percent and a peak demand shortage of 11.6 percent, In order to sustain a growth rate of 8 percent, it is estimated that the power generation capacity in India would have to increase to 306 GW in the next ten years which is 2.5 times current levels.
12 | P a g e
13 | P a g e
SECTION - 4 TECHNICAL FEATURE & EQUIPMENTS OF THE PLANT
14 | P a g e
BASIC SYSTEM DESCRIPTION Solar Photovoltaic power generator consists of solar modules in series and parallel connections, these convert solar radiations into DC electrical power at the pre-determined range of Voltages whenever sufficient solar radiation is available. The individual crystalline solar cells are connected together in a module (in series connection), which are hermetically sealed to survive in rugged weather conditions and ensures optimum performance during its ling life In order to achieve a higher system voltage, modules are installed in a row arrangement, called a string. A higher system voltage has the advantage of lesser installation work, higher efficiency of the entire plant and usage of smaller cross section cables. Calculated no. of strings is connected in parallel by cables in Junction Boxes. These junction boxes not only act as a junction point but also monitor each string output which will be fed to the central monitoring and analysis system. Outputs from many such junction boxes are connected in parallel in the Main Combiner Box (MCB). This Main Combiner Box output is fed to the central inverters/Power Control Unit (PCU) to invert solar generated DC power in to conventional 3 phase AC power. Central inverter or PCU operate on MPPT (Maximum power point tracking) mode to ensure maximum output from the solar generators at different ambient conditions. Central inverters use higher system voltages to reach very high plant efficiency. Furthermore, installations can be expanded with additions of more modules without problems. AC power from inverters will be fed to LV panel which in turn will be stepped up through transformer. Power at 11kv/22Kv will be transmitted by overhead transmission line to grid.
15 | P a g e
SECTION-5 POWER PLANT CONFIGURATION AND SPECIFICATIONS OF MAIN PLANT EQUIPMENT
16 | P a g e
The capacity of the Proposed Solar Power Plant has been fixed at 1 MWp.x 5Nos. The principle factors considered for designing and selection of proposed plant are local solar radiations, ambient conditions and electrical load characteristics of major system namely the array and power conditioning unit. Moreover, the proposed plant is situated at remote village location, so maximum use of local materials available on site for construction and to retain or preserve the original appearance of the sire and the environment are considered SR.NO. ITEM PV arrays 1.0 Modules in a string 2.0
50 Nos 18 Nos
3.0
String in a array
28Nos
4.0
Inverters
50 X 100 KVA
5.0
Transformer
5Nos
SPECIFICATION OF MAIN PLANT (A)
SOLAR PV MODULE
SR.NO.
ITEM
1.0
Output Power-Pmax (Watt)
200 Wp
2.0
Voltage at maximum power-Vmp (Volts)
28.60 V
3.0
Current at maximum power-Imp (Amps)
7.02
4.0
Open circuit voltage – Voc (Volts)
36
5.0
Short circuit current-Ise (Amps)
7.55
6.0
Type of solar PV cell
Poly Crystalline
7.0
Dimensions
1619MM x 1002MM
8.0
weight
23.50Kg
17 | P a g e
(B)
SOLAR INVERTER
SR. NO. 1.0
ITEM Nominal Voltage
230/400 volts three phase, 4 Wire,
grid
tracking
Nominal
voltage can be adjusted by ± 10% via system stepoints.
2.0
Output Frequency
50Hz ± 0.5% inverter to follow grid frequency up to ±3Hz of the nominal output frequency during normal operation
3.0
Continuous rating
100 kw at unity power factor
4.0
Max DC link Voltage Range
800 volts DC
5.0
MPPT Range
397 to 585 Volts DC
6.0
Control Type
Voltage source, microprocessor assisted output regulation
7.0
Waveform
PWM for low THD, sine wave output
8.0
THD
Less than 3 %
9.0
Efficiency
Up to 94%
10.0
Internal protection system (using electronic detection)
Internal
continuous
overload
protection inverter peak current (short circuit) protection Heatsink over
temperature
over/under
18 | P a g e
grid
protection voltage
AC
voltage protection over/under grid frequency protection Anti islanding protection
11.0
Alarm Signals
Via system fault relay (voltage free contact)
12.0
Front panel display (LCD)
LCD
panel
with
membrane
keypad displaying the following inverter
per
phase
voltage,
current, kW, kVA and frequency Grid
voltage
and
frequency
inverter (grid ) on line status PV panel voltage Solar charge current and
ambient
temperature
individual power stage heat sink and cabinet temperature solar radiation (optional ) Inverter Import & export kWh summation solar kWh summation system stepoints and event logs
13.0
Front Panel Controls (via keypad)
Auto
mode
connect selection
selection-
Inverter System
Grid
Test
Mode
off
Mode
selection Fault Reset
14.0
Front Panel Indicators
Inverter On line control power supply OK system Fault
15.0
Circuit Breakers
ACB / MCCB
16.0
RFI
Design conducted emissions
19 | P a g e
to
minimize and
radiated
both RFI
17.0
Earthing Provisions
AC bypassing to earth on inverter and DC inputs
18.0
Operating Temperature Range
5-50 degrees Celsius
19.0
Humidity
0-90% non condensing
20.0
Enclosure
Rate for IP30
21.0
Computer port
Isolated RS232 port. Provision for Mod bus protocol. WiFi, LAN protocol
22.0
Computer Access
The system includes a local access
port
as
well
as
a
telecommunication dialup facility incorporating either a standard PTSN modem or GSM modem for remote access. SCADA package will be windows based OPSComs.
23.0
System feature
Adjustable logging repetition from 1 sec to 900 seconds Storage capacity of up to 3 year with 10 min logs Time and date stamped log
entries
Time
and
Date
annotated fault log, holding the fault description and operating statistics View and change system stapoint configurations remotely Bulk
log
download
for
data
importation into a spreadsheet where applicable.
20 | P a g e
24.0
Logging Attributes
A summary of the data logging abilities supply with the
control
system for instantaneous viewing and periodic logging are listed below:
System
summations
inverter
import and export kWh Solar (C)
415V PCC x 125 Nos
SR. NO.
ITEM
Parameters Inverter volts, amps, kW, kVA, frequency Grid volts and frequency
1.0
TECHNICAL PARAMETERS
1.1
System particulars
1.1.1
Rated voltage and phases
1.1.2
Frequency
1.1.3
System earthing
21 | P a g e
Solar
panel
temp.
Ambient temperature PV panel voltage Solar charge current Heat sink & cabinet temperatures solar 415 V, 3 Phase, 4 wire radiation (with external 50 Hz pyranometer optional). Effectively earthed
1.1.4
Maximum system voltage
1.1.5
One minute power frequency withstand
457 V
voltage
2.5 kV
(a) Power circuit
1.5 kV
(b) Control circuit 1.1.6
Continuous current rating of busbars (a) PCC
1.1.7
2000A
Short circuit withstand (a) PCC
50 kA/1 sec.
1.1.8
Reference ambient
500C max.
1.1.9
Max temp of busbars at rated current
900C
2.0
CONSTRUCTIONAL REQUIREMENTS
2.1
Sheet steel thickness
2.1.1
Frames
2.5 mm cold rolled
2.1.2
Doors
2.5 mm cold rolled
2.1.3
Covers
2.0 mm cold rolled
2.2
Degree of protection
IP 52
2.3
Colour finish shade as per IS: 5
Seven tank process painting with epoxy based
2.3.1
Interior
Glossy white
2.3.2
Exterior
Shade 631
2.4
Busbar material
All alloy of E 91 E grade. For main bus bars - copper for Auxiliary bus bars fully insulated
2.4.1
Bus bra installation
2.5
Earthin bus.
22 | P a g e
Fully insulated
2.5.1
Material
2.5.2
Size
GS
(a) for PCC
By bidder
2.6
Clearances in air of live parts
5-50 degrees Celsuis
2.6.1
Phase to Phase
25.4 mm
2.6.2
Phase to earth
19.4 mm
2.7
Single front design
All panels
2.8
Draw out / Fixed type design
Rate for IP30
2.8.1
PCC-ACB
Draw out type
2.8.2
MCCB
Fixed / plug in type
2.9
Incoming supply to PCCs
Through cables
2.10
Vertical cable alley
Minimum 250 mm
2.11
Cable entry
Bottom
3.0
INCOMER CIRCUIT BREAKER FOR PCC
3.1
Circuit breaker type
Fully draw out type Air circuit breaker
3.2
No. of Phases
4 pole
3.3
Rated breaking capacity
50 kA
3.4
Short circuit withstand current
50 kA for 1 Second
3.5
Rated current
Refer enclosed SLD
3.6
Type of operating mechanism
Motorized spring charged Motor voltage, 220 V Ac, 1Ph.
3.7
Shunt trip require Yes/No
Yes
3.8
Relays / releases / control
Overload / Earth fault / short circuit / static with settable settings (Microprocessor based)
3.9
Remote communication
Through serial link, Port Rs. 485 with formation of bus wires and communication modem
3.10
Breaker Test-Service selector switch
Required
3.11
Local- Remote selector switch
Required
3.12
Minimum no. of auxiliary contacts
4 No, 4 NC spare for purchaser’s use
4.0
OUTGOING CIRCUIT BREAKER FOR PCC
4.1
Circuit breaker type
23 | P a g e
MCCB
4.2
No. of phases
TP with N
4.3
Rated breaking capacity
50 kA for 1 sec.
4.4
Type of operating mechanism
Manual
4.5
Shunt trip required
Yes
4.6
Relays / series releases
Overload / short circuit
(D)
TRANSFORMER
SR.
ITEM
NO. 1.0
GENERAL
1.1
Application
Power Transformer
1.2
Quantity
1 No.
1.3
Installation (Indoor / Outdoor )
Outdoor
1.4
Type (Auto / 2 Winding / 3 Winding)
2 Winding
1.5
Rating
1.6 MVA
1.6
Cooling
ONAN
2.0
TEMRATURE RISE
2.1
Ambient temp. maximum
45 C
2.2
Temp. Rise of oil by thermometer
50 C
2.3
Temp. Rise of winding by resistance method
55 C
2.4
Impedance at rated current frequency at 75 C
6.25%
24 | P a g e
3.0
TAPPING: Off Load Tap Changer
3.1
Tapping on winding (HV)
+5 to -5%
3.2
Total tapping range
+10
3.3
Step
2.5% ( 5 taps)
4.0
RATING
4.1
No load voltages
4.2
Frequency
5.0
TERMINAL CONNECTION
5.1
HV Winding Line end
(a) HV Winding
11 kV
(b) LV Winding
433 V
50 Hz
433 V
XLPE cable (with heat shrink terminations)
5.2
HV Winding neutral end
----------
5.3
LV Winding Line / N end
XLPE cable (with heat shrink terminations)
5.4
LV Winding neutral bushing
5.5
Earthing conductor for Transformer body
6.0
SYSTEM DATA
6.1
System voltages
(a) HV Nominal / Highest 11/12 kV (b) LV Nominal / Highest 0.433/0.457 kV
6.2
Fault levels
(a) HV (6.6kV) system 40 kA (b) LV (415V) system 50 kA
6.3
System Neutral Earthing
(a) HV (11kV) Earth through Resistor (b) LV (415V) Solidly Earth System
7.0
WINDING
7.1
Material of Winding
Copper
7.2
Winding connection & vector group
HV (11kV) Delta LV (433V) Star
7.3
Transformer neutral Type of Earthing
8.0
MISCELLANEOUS
8.1
Wheels
Separate Neutral bushing for earth connection (suitable for 1.1kV grade) (a) Material -- G.I. strip (b) Size -- 60 x 12 mm
Dyn 11
(a) HV – Not applicable (b) LV – Solidly Earthed (a) Plain / Flanged : Flanged (b) Unidirectional / Bidirectional : Bidirectional
25 | P a g e
8.2
Winding temp. indicator required
Yes
8.3
Any special final paint required (Epoxy etc.)
Epoxy painting
9.0
Additional
features
for
terminal
connection 9.1
HV cable box:
With disconnecting chamber, phase segregated type, provided with space heater thermostat
9.2
LT cable box
9.3
Separate LV Neutral bushing:
9.4
Neutral CT after bifurcation
Required for earth connection to earth pit 2000/1 A, class PS for 64R, 2000/1 A, CL 5P10, 15 VA for 51NS shall be provided
NOTES: (1) Transformers shall be provided with necessary accessories
(E)
HT CABLES
SR. NO.
ITEM
1.0
Voltage Grade
11 kV (UE) grade cables, heavy duty
2.0
Conductor
Stranded Aluminium
3.0
Conductor Screen
Semi – conducting compound
4.0
Insulation
XLPE
5.0
Inner sheath
Extruded PVC (Type ST-2)
6.0
Outer sheath
Extruded PVC (Type ST-2)
7.0
Armoring
8.0
Cable Operating Temperature
Galvanized steel strips for multi-core cables and non-magnetic Aluminium wires for single core cables 90 C
9.0
Short
circuit
withstand
current 40kA for 1 sec.
capacity 10.0
Short circuit withstand temperature
(F)
LT CABLES
SR. NO.
ITEM
1.0
POWER CABLE
1.1
Voltage Grade
26 | P a g e
250 C
UNIT
V/V
1100V for 415V system
1.2
Frequency
Hz
50
1.3
Earthing system
-
1.4
Conductor
-
1.4.1
Material
-
1.4.2
Max withstand Temp
-
(a) Normal condition
C
90
(b) Short circuit condition
C
250
1.4.3
Conductor type
-
Stranded
1.4.4
Grade
-
H4
1.5
Insulation
-
1.5.1
Material
-
XLPE
1.5.2
Reference standard
-
IS 7098, Part I and Part II
1.6
Inner Sheath
-
1.6.1
Material
-
FRLS PVC
1.6.2
Type
-
ST2
1.7
Outer Sheath
-
1.7.1
Material
-
FRLS PVC
1.7.2
Type
-
ST2
(G)
EARTHING & LIGHITNG PROTECTION
Solidly earthed system for 415V system
Annealed Cu
CODES & STANDARDS The earthing of all outdoor equipment and provision of associated earthing systems, electrodes and connections shall be in accordance with the recommendations in the latest IEEE 80/IS 3043. DESIGN CRITERIA GROUNDING SYSTEM The grounding design calculation shall conform to ANSI / IEEE Standard 802000. Earth electrodes shall be provided throughout the plant areas along with the main earth grid. The number of earth electrodes shall be according to achieve the total earth grid resistance less than one (1) ohm. Earth electrodes shall be provided in earth pits. The earth pits shall be of two types namely treated with
27 | P a g e
test links and untreated. Earth electrodes shall be of heavy duty GI pipes, 40 mm dia and 3 meter long. The main buried grid conductors shall be connected to all the earth electrodes to form a total earth grid.
28 | P a g e
GROUNDING MATERIAL Galvanised steel flats of required size shall be used as per approved design. In any case the minimum size shall be 75 x 10 mm. GS strip for earthing conductor. Treated earth pits shall conform to relevant INDIAN Standards. The earth grid shall be installed specified / approved depth of minimum 600mm. EQUIPMENT EARTHING The frames of all electrical equipment and structural steel work shall be earthed by connection to earth grid by branches of same cross sectional area of the earth grid. LIGHTINING PROTECTION SYSTEM Power plant needs protection against Lighting. The system will be designed as per IS: 2309 and Indian Electricity Rules. Vertical air termination of 40mm diameter, 3 M long shall be provided above highest point of array to provide radius of protection full array. (H)
STRUCTURAL MOUNTING EQUIPMENT
SR. NO.
ITEM
1.0
Type
Ground Mounting
2.0
Material
MS Galvanized
3.0
Overall dimension
As per design
4.0
Coating
Hot dip (Galvanized) Minimum of 130 Micron size
5.0
Wind rating
150 km / hr
6.0
Tilt angle
30
7.0
Foundation
PCC
8.0
Fixing type
SS 304 Fastners
29 | P a g e
SECTION - 6 OPERATION AND MAINTENANCE
30 | P a g e
OPERATION AND MAINTENANCE PHILOSOPHY The proposed Organization structure for the operation and maintenance (O&M) of the power plant is presented in the exhibit.
In order to ensure a high level of
performance of the power plant, it is proposed to induct experienced O&M engineers from the very beginning of the project. BASIC STRUCTURE OF THE O&M TEAM The basic structure and the broad functional area within the O&M organization would be as follows: The Plant Manager would have the primary responsibility for the O&M of the power plant.
The organization will compromise of four broad functional areas viz.
Operation, Maintenance, Technical and Administration. The basic duties covered under each of these functional areas would be as follows: Operation (a)
Operation of main generating equipment, switch yard and other auxiliary plant.
(b)
Except for the Power Station Superintendent all other operating personnel would work one shift basis.
(c)
The day to day operation of the power plant will be controlled by the Manager who will be assisted by the Control room operators and engineers.
Maintenance (a)
Maintenance of mechanical and electrical plant, control systems, buildings, roads, drainages and sewage systems etc.
(b)
Operation of the plant, planning and scheduling maintenance works and deciding the requirement of spare parts
(c)
The Plant Manager will be assisted by departmental engineers, who take care of the maintenance aspects of all mechanical, electrical and I&C requirement
31 | P a g e
(d)
Trained technicians will be employed to assist the maintenance group in day to day maintenance of the plant.
Administration The main responsibilities of this department will be as follows: (a)
Purchase
(b)
Plant Security
(c)
Liaison with local labour officers
(d)
Stores management
(e)
Medical Services
(f)
Transport services
FACILITIES TO BE EXTENDED TO THE EMPLOYEES The number of employees required for operation of the proposed power plant will be around 10 numbers.
The personnel required for administration and finance &
accounts also will be provided. The following facilities will be provided in the power plant. (a)
Administration Building and Technical Office
(b)
Stores
(c)
Time and security offices
(d)
First Aid and Fire Fighting Station
(e)
Toilets and Changes rooms
32 | P a g e
Ordinary Maintenance Ordinary Maintenance, which covers routine checking and minor refurbishment activities to be performed according to operation manuals of components / equipments in operating conditions. Emergency Maintenance Emergency Maintenance, which is corrective maintenance to be performed when a significant failure occurs.
To minimize forced outages duration, an effective
Emergency Maintenance must be supported by: (a)
A proper stock of spare parts
(b)
Permanent monitoring and diagnostic systems for main components.
Maintenance Plan and Scheduled Maintenance Scheduled maintenance is carried our according to maintenance plan, which should be discussed and optimized according to the needs of the customer / client. The maintenance plan is based on scheduled outages for the following components: (a)
Cleaning of Solar Module
(b)
Power Processing System
(c)
Switchyard equipment
MAINTENANCE MANAGEMENT SYSTEM The maintenance of this plant will be carried out as per the above philosophy. This system aims at maximizing the availability of the plant, while ensuring minimum maintenance cost and safety of the plant and personnel. SPARE PARTS MANAGEMENT SYSTEM
33 | P a g e
The primary objective of spare part management system will be to ensure timely availability of proper spare parts for efficient maintenance of the plant without excessive build-up of non-moving and slow moving inventory. The spare parts management system for this project will cover the following areas: (a)
Proper codification of all spares and consumables
(b)
Spare parts indenting and procurement policy
(c)
Ordering of critical mandatory and recommended spares
(d)
Judicious fixation of inventory levels and ordering levels for spare parts based on experience.
(e)
Development of more than one source of manufacturer / supplier whenever practicable.
AVAILABILITY OF O & M MANUALS All contracts include provision of at least 6 sets of details O&M manuals, which will be distributed to all departments concerned well in advance from the commissioning date of the power plant to avoid problems in preparation of commissioning documents as well as proper installation and commissioning procedures of various equipments. SPECIAL TOOLS AND TACKLES All contracts will include the provision for supply of one set of all types of special tools and tackles, which are required for installation, commissioning and proper maintenance of plant and equipment.
34 | P a g e
CHECKLISTS AND PROTOCOL A detailed checklist for the various equipments, supplemented with the checklist submitted by the supplier shall be drawn and logged for future reference. This will also form part of the plant’s base history / datum. Whenever an equipment in commissioned, the important parameters of that particular equipment should be observed for a period of eight hours and the readings shall be logged as per the log sheets. These activities shall be performed in the presence of the customer / consultant and a protocol shall be signed. SAFETY AND PROTECTION The importance of safety and the protection of personnel and equipment cannot be overemphasized. The system must be designed to minimize hazards to operation and maintenance personnel, the public, and equipment. The control subsystem must be equipped with various fuses, built-in fault detection and protection algorithms to protect the users, the loads, and the PV system equipment. The safety of an operator or technician is of the utmost importance. Personnel must be protected from electric shock by following all available safety practices. Such as displaying high voltage warning signs wherever necessary. In general, the system must adhere to the IS Codes and standards dealing with safety issues. Some of the important safety criteria are as follows: (a)
Electrical components should be insulated and grounded
(b)
All high voltage terminations (> 50 Vdc) should be properly covered and insulated
(c)
All component with elevated temperatures should be insulated against contact with or exposure to personnel
(d)
Structures should be grounded and ground fault relays installed to give warning of ground faults in the array or other electrical components.
35 | P a g e
SECTION - 7 SWOT ANALYSIS
36 | P a g e
SWOT ANALYSIS. Non – Conventional Sources, which are renewable in nature, are termed as the alternate sources of energy. The Challenges of the present – energy scenario offer us a window of the opportunity in the form of renewable energy sources. The Power from the sun is clean , silent , limitless and free. Photovoltaic (PV) process releases no CO2 , SO2 or NO2 gases which are normally associated with burning finite fossil fuel reserve and don’t contribute to global warming . Solar power shall augment the need of peak power needs & increases the grid reliability I.e , Voltage and frequency. Solar Powered grid connect plants can act as tail end energizes , which in turn reduces the transmission and distribution losses. (a)
Geographically India is situated at northern hemisphere near the Equator. So India gets maximum solar irradiation and there is ample of scope to produce the power from solar PV. But till now this area is totally virgin area for producing power.
(b)
This is true that solar PV efficiency is very low compared to other power generation systems , Lots of R&D is going on the improve the efficiency. Solar PV generates electricity only at day time , So the proposed solar PV Power plant generates power on an average only about six hours in day time.
(C)
India is potentially one of the largest markets for solar energy in the world. The estimate4d potential of power generation through solar photovoltaic system is about 20 MW/Sq.km in India. It is useful for providing grid quality, reliable power in rural area where the line voltage is low and insufficient cater to connected load. Recent Government incentives and policies have been providing the momentum for PV in India . The Government of India already declared national Action plan on climate change released in mid 2008, identifies eight critical mission – one of which is the National Solar Mission.
(d)
In comparison to other sources of power generation, the PV solar power is totally dependent in nature . The capacity utilization factor of such type of plant is only 19%. Because averagely in the year we get 6 hr sunlight
37 | P a g e
in a day . Only this particular interval solar plant generates electricity. In comparison to other conventional power generating units, solar power generating unit has many advantages like.
(a)
No fuel is required for power generation.
(b)
Operation & Maintenance Manpower required is less.
( c)
Plant will be running smoothly for a long period as compared to other conventional power generation units.
(d)
In environmental perspective , solar power plant generates clean energy and gets maximum clean development mechanism (CDM) benefit as compared to other conventional power generation units.
Considering all the above points, solar power generating potential is always ahead of all other conventional power generating units in economical & Environment point of view.
38 | P a g e
SECTION - 8 PLANT LAYOUT & PROJECT IMPLEMENTATION
39 | P a g e
INTRODUCTION.
This layout of the plant and facilities for the proposed solar power plant is largely dictated by its location, shape and road etc. Involving minimum eviction, the wind rose pattern, land use pattern of adjoining area and the direction of power evacuation.
IMPLEMENT CONCEPT The project is planned to be implemented at the earliest . The most essential aspect regarding the implementation of this project is to ensure that the project is completed with in the schedule , spanning 6 months from the placement of purchase order. A good planning , scheduling , and monitoring program is imperative to complete the project on time and without cost overruns.
The project zero date start once the kick- off meeting has taken place and the advance payment has been received.
PROJECT IMPLEMETATION STRATEGY.
It is envisaged that the project will have the below mentioned phase of activities . These phases are not mutually exclusive ; to implement the project on fast track basis some degree of overlapping is envisaged.
40 | P a g e
Phase I
Project Development
Phase II
Finalization of the Equipment and contracts
Phase III
Procurement and Construction.
Phase IV
Plant Commissioning
SECTION – 9 ESTIMATED PROJECT COST
41 | P a g e
BASIS FOR COST ESTIMATION The capital cost of the plant has been estimated taking into account the cost of civil & structure works, transportation, installation, testing, commissioning charges and contingencies. Land cost is not considered as land is already available. The cost of material and electrical equipment has been estimated based on budgetary quotation received previous quotations for other projects and in house cost data suitable altered. Excise duty is exempted as per MNRE consideration. Packing, forwarding , inland transportation and insurance at the rate of 2.5% for all equipment and systems including spares have been considered. Erection, testing and commissioning charges are considered as 8% of supply cost for mechanical and electrical equipment. 3% of the equipment cost has been considered towards cost of initial spares. Cost of civil works has been estimated based on data available for similar projects. Power plant life is considered as 25 years.
42 | P a g e
SECTION – 10 ESTIMATED POWER GENERATION COST
43 | P a g e
COST OF POWER GENERATION Basis for Generation Cost Estimation Debt-Equity Ratio shall be 70:30 Rate of interest on loan shall be 10.0% p.a. Depreciation shall be 10.34% for plant & machinery and 3.34% for Civil work The working capital is insurance expenses for one year in advance and one month requirement of spares and consumables Eligibility for working capital loan is 75% of total working capital & interest rate on the loan is 12% p.a.
44 | P a g e
Refrences: http://www.businesswire.com/news/home/20110927005580/en/Satcon-Chosen-Landmark-5Megawatt-Project-Arizona http://www.google.co.in/search?sourceid=chrome&ie=UTF-8&q=Project+of+5+Mega+Watt http://www.bloomberg.com/news/2012-01-04/world-bank-backed-azure-completes-5megawatt-solar-power-project.html http://www.reeep.org/485.17860/greenergy-renewables-pvt-ltd.htm http://www.airvoicegroup.in/gepl.htm http://gpenergy.net/ http://www.outbacksolarproject.com/2011/10/outback-5-megawatt-solar-project.html http://green.tmcnet.com/channels/solar-power/articles/223414-satcon-chosen-landmark-5megawatt-project-arizona-western.htm http://www.renewablewire.com/solar-power/satcon-chosen-for-5-megawatt-solar-project-byarizona-western-college.html
Text Book: Project Finance In Theory And Practice- Stefano Gatti Project Appraisal and Finance – Prasanna Chandra
45 | P a g e
Detailed Project Report Solar Power Plant Pdf Download Free
Power Generation Options (Solar PV) for North Gaza Emergency Sewage Treatment Plant Feasibility Study Table of Contents Page 12. ANNEX 160 12.1 Detailed Site Description 160 12.1.1 Areas Designated for PV Systems 160 12.1.2 Electrical Infrastructure 166 12.1.3 Additional Site Infrastructure 174 12.1.4 External Interfaces 175. Line, of approximately 29 km with a wayleave of 15m, would be constructed from the solar power plant and would terminate on the 34.5kV bus at the Bolgatanga Substation, in the Bolgatanga Municipality also in the Upper East Region. The project is titled the “40MW Bongo Solar Power Project” (hereinafter referred as the “Project”). The proposed Power Plant will have Solar PV modules, String Inverters as the major components & other accessories for the Power production. All the necessary auxiliary facilities of the Power Plant like Plant Monitoring system, Safety equipments, Instrumentation, Control system etc., will be provided for the Power Plant.
Solar Power Plant Working Principle
Solar PV Power Generation System Detailed Project Report SOLAR PV POWER GENERATION SYSTEM Detailed Project Report For 20.00 KWp Solar PV Grid Connected System PROJECT PROVIDING ON GRID TYPE 20.00KWp SOLAR PV POWER PLANT AT FACTORY REF. SM/RRD/SPV/OH 14000238 RR Donnelley Publishing India Private Limited. For the design of the mirror field for the CNRS (Centre National de la Recherche Scientifique) project of a several MWe solar energy conversion power plant, an analysis of this concentration.